edit RELEASE-NOTES
to be accurate
update docs/THANKS
make sure all relevant changes are committed on the master branch
tag the git repo in this style: git tag -a curl-7_34_0
. -a annotates the
tag and we use underscores instead of dots in the version number. Make sure
the tag is GPG signed (using -s).
run "./maketgz 7.34.0" to build the release tarballs. It is important that you run this on a machine with the correct set of autotools etc installed as this is what then will be shipped and used by most users on *nix like systems.
push the git commits and the new tag
gpg sign the 4 tarballs as maketgz suggests
upload the 8 resulting files to the primary download directory
edit Makefile
(version number and date),
edit _newslog.html
(announce the new release) and
edit _changes.html
(insert changes+bugfixes from RELEASE-NOTES)
commit all local changes
tag the repo with the same name as used for the source repo.
make sure all relevant changes are committed and pushed on the master branch
(the web site then updates its contents automatically)
We do releases every 8 weeks on Wednesdays. If critical problems arise, we can insert releases outside of the schedule or we can move the release date - but this is very rare.
Each 8 week release cycle is split in two 4-week periods.
During the first 4 weeks after a release, we allow new features and changes to curl and libcurl. If we accept any such changes, we bump the minor number used for the next release.
During the second 4-week period we do not merge any features or changes, we then only focus on fixing bugs and polishing things to make a solid coming release.
Based on the description above, here are some planned release dates (at the time of this writing):